Ososa First Junction, Opposite Rite Foods Factory, Sagamu/Benin Expressway · +234 701 634 2227 Construction   25% → 100% by 30 September 2026

The Station is the product.

Customers experience TYard® through the Station before they experience the work. A clean, well-lit, professionally-signed facility with disciplined movement, marked bays, working drainage, fire equipment in place and uniformed staff — selling the business before our prices are even discussed.

Location

Ososa First Junction. On the Sagamu/Benin Expressway.

Ideally located opposite the Rite Foods factory, directly on one of Nigeria's busiest haulage corridors.

The Sagamu–Benin Expressway carries traffic between Lagos, Ogun, Ondo and Edo States — a constant flow of the trucks we serve. From Ososa, we are walk-in distance for the RFL transporter panel and within easy reach of the wider east-bound haulage network.

16
Service-line bays
12
Specialised service lines
24/7
Security operations
06:30
Daily opening time
OSOSA FIRST JUNCTION · OGUN STATE Opposite Rite Foods. On the Sagamu/Benin Expressway.
Facility layout

Twelve service-line bays. Plus everything around them.

A real workshop is more than its bays. Every supporting facility has been designed in from day one.

SERVICE-LINE BAYS

  • General Servicing
  • Mechanical / Engine
  • CNG Conversion
  • Transmission
  • Suspension / Steering
  • Air Brakes
  • Electrical
  • Injector Systems
  • Exhaust
  • Fabrication (with separate paint booth)
  • Tyre / Vulcanising
  • Upholstery / Interior

CUSTOMER & DRIVER

  • Customer reception area
  • Driver lodging
  • Washroom facilities
  • On-site canteen
  • Waiting area with live job status
  • Drivers' welfare officer on duty

OPERATIONS & SAFETY

  • Parts warehouse with cycle-count protocols
  • Security control room with CCTV
  • HSE office
  • Fire response equipment
  • Spill response & environmental compliance
  • Yard movement plan: arrival → bay → exit
Construction roadmap

From 25% today to 100% by the end of September.

A single integrated master schedule covering civils, MEP, equipment, IT, signage, HSE and operations. Weekly status to the CEO's office every Monday.

TODAY · 18 MAY 2026

~25% completion

Civils under way. Master schedule live. Construction partners 1st Truckstops® (project management) and 1st Konstruct® (construction) executing weekly priorities.

30 JUNE 2026

Civils to 60%

Major structural work substantially advanced. Equipment specifications finalised. First orders placed for long-lead items via TGL® International Trade.

31 AUGUST 2026

Civils to 90% · MEP rough-in complete

Imported equipment beginning to arrive at Ososa. Pre-positioned installation crews ready — no equipment sitting in crates.

30 SEPTEMBER 2026

Construction substantially complete

100% civils / 95% MEP. Equipment installation under way across all 16 service-line bays. Spare-parts cargo inventoried.

15 OCTOBER 2026

All bays operable · dry-run rehearsal

All equipment commissioned. Facility staff recruited and trained. Brand standards applied. Customer-journey map dry-run with TGL®Trucking trucks and mock walk-ins.

25 OCTOBER 2026

Joint readiness review

Full operating-day dry run. Business Team and Facility Team joint review. Issues identified and fixes implemented before 1 November.

28 OCTOBER 2026

CEO go / no-go sign-off

Final sign-off by the Office of the CEO.

1 NOVEMBER 2026

Pre-commercial launch

Doors open for TGL®Trucking and pilot 3rd-party owners.

Daily operating cadence

The rhythm of a TYard® Station day.

06:30

Facility opens. Security shift change. Yard cleaning crew complete.

07:00

Daily safety brief. Bay assignments issued. Equipment readiness checks.

08:00

First customer reception. Doors open for walk-ins and scheduled bookings.

19:00

Facility closes for new bookings. 24/7 security continues. Daily exception log to GM.

A weekly facility report is delivered to the Office of the CEO. Equipment downtime is held below 5% of scheduled operating hours. Stock-out rate for fast-moving items is held below 3% in any month. Every HSE incident, accident or near-miss is logged within four hours, root-caused within seven days and mitigated within thirty.

OSOSA · OGUN STATE A welcomed presence in the community
Community presence

A welcomed, contributing presence — not a gated facility.

Ososa is a community. TYard® is being built to be welcomed. Engagement with the Ososa community leadership, the Ogun State Ministry of Commerce and Industry, the Federal Road Safety Corps, the Vehicle Inspection Office and Sagamu Local Government Area is a permanent part of how we operate — not a launch-day event.

  • Quarterly community engagement budget
  • Youth skills outreach
  • Road-safety days
  • Community clean-up activities
  • Two community apprenticeship slots filled by start of 2027
Beyond Ososa

The first of many.

Ososa is the prototype. Lagos, Abuja, Itapele and inland sites follow.

What we build at Ososa — the layout, processes, signage, equipment placement, safety protocols and operating rhythms — becomes the template for every subsequent TYard® Station. We will replicate it with minimal variation.

Visit the Station.

Tours by appointment from October 2026. Speak to us in the meantime about the launch.